In this blog you will find the correct answer of the Coursera quiz Initiating and Planning Projects Coursera All weeks Quiz mixsaver always try to brings best blogs and best coupon codes
Module 2 Quiz
1.
Question 1
True or False: A Project is defined as being unique and temporary, with an undefined start and finish.
1 point
- False
- True
2.
Question 2
We discussed three types of matrix organizations, they are:
1 point
- Weak, Medium Strength and Strong
- Weak, Balanced and Strong
- Light, Medium and Heavy
- Light, Mid-strength and Strong
3.
Question 3
In a projectized organization:
1 point
- The project manager acts as manager of the team.
- A project manager is not assigned to the team.
- The functional manager has all of the power.
- Team members are never assigned to the project full time.
4.
Question 4
True or False: The best organization to use to run a project will always be the projectized organization.
1 point
- False
- True
5.
Question 5
The five project management process groups as described in the PMBOK® Guide and discussed in the preceding lesson are:
1 point
- Initiating, planning, executing, monitoring and controlling, closing
- Kickoff, requirements, plan, schedule, control
- Requirements, design, development, testing, implementation
- Define, measure, analyze, improve, control
6.
Question 6
The three components of the triple constraint are:
1 point
- Scope, Cost, Time
- Scope, Performance, Cost
- Scope, Quality, Cost
- Scope, Performance, Time
7.
Question 7
You have finished planning and have begun executing the project when the client asks if you would add some important features to the product of the project. How are the triple constraints affected?
1 point
- Adding features will require additional cost but not time
- Cost must remain constant because resources are limited
- Time and cost may both be affected
- Scope and quality would be affected but not cost
8.
Question 8
The primary role of the project manager is:
1 point
- Project initiation
- Communication
- Measuring performance
- Distributing work packages
9.
Question 9
As discussed in the preceding lesson, The PMBOK® Guide knowledge areas that have processes in the Initiating process group are:
1 point
- Project Integration Management and Project Stakeholder Management
- Project Integration Management and Project Scope Management
- Project Integration Management and Project Time Management
- Project Integration Management and Project Quality Management
10.
Question 10
As discussed in the preceding lesson, The PMBOK® Guide describes 10 Project Management Knowledge Areas. Identify 3 out of the 10:
1 point
- Cost, Integration, Process
- Cost, Scope, Time
- Quality, Process, Scope
- Contracts, Process, Risk
Module 3 Quiz
1.
Question 1
The definition of a stakeholder includes:
1 point
Organizations impacted by your project but not people, they are all part of the impacted organizations.
People and organizations that are not impacted by your project.
The people or organizations that are positively or negatively impacted by your project.
People who are impacted by your project, but not organizations impacted by your project.
2.
Question 2
True or False: If you are not certain who your stakeholders are, asking who will use the product or service being created can be helpful.
1 point
False
True
3.
Question 3
If a stakeholder has high interest and high power then as the project manager you:
1 point
Can ignore them, they are as you need them to be.
Focus your time and attention on them, they are very impactful to your project and you want to keep them engaged and positive.
Can try to move them to be low interest and low power so that they do not take up too much of your time.
Can try to move them to be high interest and low power so they do not get in your way.
4.
Question 4
You just came from a meeting with one of your project stakeholders, he knew about your project and was not against it, but did not seem to be particularly interested in it either. How would you classify him?
1 point
Neutral
Supportive
Resistant
Unaware
5.
Question 5
True or False: The Project Sponsor is responsible for stakeholder expectations management.
1 point
False
True
6.
Question 6
Who is the stakeholder that will ultimately use the product or service you are creating?
1 point
Project Team
Customer/User
Project Manager
Sponsor
7.
Question 7
One way to classify your stakeholders is to use the Power/Interest Grid. If a stakeholder is low interest / low power, what should the Project Manager do?
1 point
Keep satisfied
Monitor
Keep informed
Manage closely
8.
Question 8
Your stakeholder register is your primary output and should at least contain:
1 point
Job descriptions, identification information, and stakeholder classification
Assessment information, identification information, and stakeholder classification
Assessment information, scope information, and stakeholder classification
Assessment information, identification information, and risk classification
9.
Question 9
You have a stakeholder on your project who has a reputation as being very difficult. He dislikes change and argues against any suggested updates to the way in which his department does their work. The project you are leading is going to significantly impact at least two processes used by his team. Which do you think is the best response to the situation?
1 point
Ignore him and start the project without him. You will include him when you absolutely have to.
Start the project when you know he’s out of town and send him a meeting invite to cover your tracks.
Seek him out and begin to open communications with him about what is changing and why.
10.
Question 10
Identify the five engagement levels of stakeholders:
1 point
Unaware, resistant, strong-willed, supportive, leading
Unaware, resistant, neutral, supportive, leading
Unaware, resistant, neutral, supportive, oblivious
Unaware, resistant, strong-willed, supportive, sponsor
Module 4 Quiz
1.
Question 1
One of the ways a Project Charter can help you as a project manager is:
1 point
It helps you hire team members.
It does not help you as a project manager because it is for the sponsor.
It describes your authority level as the project manager.
It keeps your authority level vague, so you can do what you want.
2.
Question 2
The Scope Management section of your project plan document would include information on:
1 point
Who can suggest changes to the project.
How to ask for more money for the project.
What type of scheduling software to use.
How risks are to be managed.
3.
Question 3
True or False: An important part of the project scope statement is exclusions or out of scope items.
1 point
True
False
4.
Question 4
As you plan your project, you do so thinking that all team members will be assigned to your project for at least 50% of their available time. This is an example of:
1 point
Poor planning.
A project demand.
Wishful thinking.
An assumption.
5.
Question 5
True or False: The WBS should completely depict the scope of your project that if something is not in the WBS it is because it is NOT part of the project.
1 point
True
False
6.
Question 6
The 8-80 rule refers to:
1 point
Work packages should be between 8 and 80 hours of effort.
Work packages should NOT be between 8 and 80 hours of effort.
Never allow your team to work more than 8 hours per day or 80 hours during a 10-day work period.
Work packages over 80 hours should be split between multiple resources.
7.
Question 7
Project scope differs from product scope in that:
1 point
Project scope completion is measured against the features, functions, and product requirements.
Project scope is the work that needs to be accomplished to deliver a product, service, or result.
Product scope completion is measured against the project management plan including all subsidiary plans.
8.
Question 8
True or False. The Project Charter is a document issued by the project initiator or sponsor that formally authorizes the existence of a project. It provides the project manager with the authority to apply organizational resources to project activities.
1 point
True
False
9.
Question 9
The Project Scope Statement should include the following:
1 point
Project exclusions, project constraints, project plan.
Project deliverables, project constraints, project team members.
Project exclusions, project charter, project assumptions.
Project deliverables, project constraints, project assumptions.
10.
Question 10
True or False: A Work Breakdown Structure (WBS) is a deliverable-oriented hierarchical decomposition of the work to be executed by the project team.
1 point
True
False
Module 5 Quiz
1.
Question 1
True or False: Influence means you have the right to apply resources, make decisions and give approvals.
1 point
False
True
2.
Question 2
Which one of these is an example of role conflict:
1 point
When two team members are trying to complete the same task.
When a team member is late completing a task.
When a team member does not know why he or she should do something.
When a team member does not know how to do his or her job.
3.
Question 3
Two team members disagree on how to solve a project issue. They express their disagreement and then engage in a professional debate. This is an example of:
1 point
Unproductive conflict.
Healthy conflict.
Unhealthy conflict.
Unrealistic conflict.
4.
Question 4
You and another project manager disagree over whether a team member should work on your team or on her team. You decide that the team member can work for the other project manager in the afternoon and the other project manager says it is OK for the team member to work for you in the morning. The truth is you both wanted this person fulltime. The conflict resolution approach you have both used is:
1 point
Confronting
Smoothing
Compromising
Forcing
5.
Question 5
True or False: Conflict management is the process by which the project manager uses appropriate managerial techniques to deal with the inevitable disagreements that develop among those working toward project accomplishment.
1 point
True
False
6.
Question 6
Some of the major sources of conflict that a project manager may influence are:
1 point
Project management, project priorities, project team
Personality conflict, schedules, resources
Personality conflict, network diagram, resources
Project charter, schedules, resources
7.
Question 7
What are the 5 approaches to conflict discussed in the Project Human Resources Management Lesson?
1 point
Confronting, Challenging, Smoothing, Forcing, Avoiding.
Confronting, Compromising, Smoothing, Uninterested, Challenging.
Communicating, Compromising, Smoothing, Forcing, Avoiding.
Confronting, Compromising, Smoothing, Forcing, Avoiding.
8.
Question 8
True or False: Project Human Resource Management includes the processes that organize, manage, and lead the project team.
1 point
True
False
9.
Question 9
True or False: Each person involved in the project should be assigned, but doesn’t always need to know his or her role and responsibility.
1 point
True
False
10.
Question 10
What does RAM stand for:
1 point
Responsibility Activity Matrix
Responsibility Action Matrix
Responsibility Ambiguity Matrix
Responsibility Assignment Matrix
Final Exam
1.
Question 1
True or False: A Project is defined as being unique and temporary, with an undefined start and finish.
1 point
True
False
2.
Question 2
We discussed three types of matrix organizations, they are:
1 point
Weak, Balanced and Strong
Light, Medium and Heavy
A.Weak, Medium Strength and Strong
Light, Mid-strength and Strong
3.
Question 3
In a projectized organization:
1 point
A project manager is not assigned to the team.
The project manager acts as manager of the team.
Team members are never assigned to the project full time.
The functional manager has all of the power.
4.
Question 4
The five project management process groups as described in the PMBOK® Guide and discussed in the preceding lesson are:
1 point
Requirements, design, development, testing, implementation
Define, measure, analyze, improve, control
Initiating, planning, executing, monitoring and controlling, closing
Kickoff, requirements, plan, schedule, control
5.
Question 5
The three components of the triple constraint are:
1 point
Scope, Quality, Cost
Scope, Performance, Time
Scope, Cost, Time
Scope, Performance, Cost
6.
Question 6
The primary role of the project manager is:
1 point
Measuring performance
Project initiation
Communication
Distributing work packages
7.
Question 7
The PMBOK® Guide and in the preceding lesson describes 10 Project Management Knowledge Areas. Identify 3 out of the 10:
1 point
Cost, Scope, Time
Contracts, Process, Risk
Quality, Process, Scope
Cost, Integration, Process
8.
Question 8
The definition of a stakeholder includes:
1 point
The people or organizations that are positively or negatively impacted by your project.
Organizations impacted by your project but not people, they are all part of the impacted organizations.
People and organizations that are not impacted by your project.
People who are impacted by your project, but not organizations impacted by your project.
9.
Question 9
If a stakeholder has high interest and high power then as the project manager you:
1 point
Can ignore them, they are, as you need them to be.
Can try to move them to be low interest and low power so that they do not take up too much of your time.
Can try to move them to be high interest and low power so they do not get in your way.
Focus your time and attention on them, they are very impactful to your project and you want to keep them engaged and positive.
10.
Question 10
Who is the stakeholder that will ultimately use the product or service you are creating?
1 point
Project Team
Project Manager
Customer/User
Sponsor
11.
Question 11
One way to classify your stakeholders is to use the Power/Interest Grid. If a stakeholder is low interest / low power, what should the Project Manager do?
1 point
Monitor
Manage closely
Keep satisfied
Keep informed
12.
Question 12
Your stakeholder register is your primary output and should at least contain:
1 point
Assessment information, identification information, and stakeholder classification
Assessment information, scope information, and stakeholder classification
Assessment information, identification information, and risk classification
Job descriptions, identification information, and stakeholder classification
13.
Question 13
You have a stakeholder on your project who has a reputation as being very difficult. He dislikes change and argues against any suggested updates to the way in which his department does their work. The project you are leading is going to significantly impact at least two processes used by his team., Which do you think is the best response to the situation?
1 point
Seek him out and begin to open communications with him about what is changing and why.
Ignore him and start the project without him. You will include him when you absolutely have to.
Start the project when you know he’s out of town and send him a meeting invite to cover your tracks.
14.
Question 14
Identify the five engagement levels of stakeholders:
1 point
Unaware, resistant, neutral, supportive, oblivious
Unaware, resistant, strong-willed, supportive, sponsor
Unaware, resistant, neutral, supportive, leading
Unaware, resistant, strong-willed, supportive, leading
15.
Question 15
One of the ways a Project Charter can help you as a project manager is:
1 point
It keeps your authority level vague, so you can do what you want.
It helps you hire team members.
It does not help you as a project manager because it is for the sponsor.
It describes your authority level as the project manager.
16.
Question 16
The Scope Management section of your project plan document would include information on:
1 point
How risks are to be managed.
Who can suggest changes to the project.
How to ask for more money for the project.
What type of scheduling software to use.
17.
Question 17
As you plan your project, you do so thinking that all team members will be assigned to your project for at least 50% of their available time. This is an example of:
1 point
An assumption.
A project demand.
Poor planning.
Wishful thinking.
18.
Question 18
The 8-80 rule refers to:
1 point
Work packages should NOT be between 8 and 80 hours of effort.
Work packages should be between 8 and 80 hours of effort.
Work packages over 80 hours should be split between multiple resources.
Never allow your team to work more than 8 hours per day or 80 hours during a 10-day work period.
19.
Question 19
Project scope differs from product scope in that:
1 point
Product scope completion is measured against the project management plan including all subsidiary plans.
Project scope is the work that needs to be accomplished to deliver a product, service, or result.
Project scope completion is measured against the features, functions, and product requirements.
Product scope is the work that needs to be accomplished to deliver a product, service, or result.
20.
Question 20
The Project Scope Statement should include the following:
1 point
Project exclusions, project charter, project assumptions.
Project deliverables, project constraints, project assumptions.
Project deliverables, project constraints, project team members.
Project exclusions, project constraints, project plan.
21.
Question 21
True or False: Influence means you have the right to apply resources, make decisions and give approvals.
1 point
True
False
22.
Question 22
Which one of these is an example of role conflict:
1 point
When a team member does not know how to do his or her job.
When a team member does not know why he or she should do something.
When two team members are trying to complete the same task.
When a team member is late completing a task.
23.
Question 23
You and another project manager disagree over whether a team member should work on your team or on her team. You decide that the team member can work for the other project manager in the afternoon and the other project manager says it is OK for the team member to work for you in the morning. The truth is you both wanted this person fulltime. The conflict resolution approach you have both used is:
1 point
Forcing
Compromising
Confronting
Smoothing
24.
Question 24
Some of the major sources of conflict that a project manager may influence are:
1 point
Personality conflict, schedules, resources
Project charter, schedules, resources
Project management, project priorities, the project team
Personality conflict, network diagram, resources
25.
Question 25
What are the 5 approaches to conflict discussed in the Project Human Resources Management Lesson?
1 point
Confronting, Compromising, Smoothing, Forcing, Avoiding.
Communicating, Compromising, Smoothing, Forcing, Avoiding.
Confronting, Compromising, Smoothing, Uninterested, Challenging.
Confronting, Challenging, Smoothing, Forcing, Avoiding.
Important Links:
- Advanced Algorithms and Complexity Coursera Week 1 Quiz
- Business Analytics for Decision Making Coursera Week 1 Quiz
- Epidemiology: Successful Career Development Coursera Week 1
- How Things Work: An Introduction to Physics week 1
- Introduction to Public Speaking Coursera week 1 Quiz